Go to main content

P12-201-4532 NA Klamath Project, OR-CA. View of 8" pipe being removed due to bolts breaking at connection to 84" RCP (seen at the bottom). This had been completely backfilled and Constr. Inspector (D.W. Stein) had requested that the contractor dig it out; February 1978; USBR photo by D.W. Stein

Metric
From
To
Interval
Export
Download Full History